Ascot targets August restart at Premier mill after funding

Published: 2025-04-15 14:57 Author: Jackson Chen
Source: MINING.COM (Original Article)

AI Analysis & Insights

Ascot Resources Targets August Restart for Premier Gold Project with New Funding

Summary: Ascot Resources secures C$61.1 million to restart its Premier gold project in British Columbia, aiming for production resumption in August.

Introduction

Ascot Resources (TSX: AOT), a Vancouver-based mining company, has announced plans to restart production at its Premier gold project in northwestern British Columbia by early August. This follows the successful completion of a C$61.1 million ($44m) financing round, which will fund critical upgrades and operational enhancements at the historic mine site.

Funding and Operational Upgrades

The newly secured funds will address key operational bottlenecks, particularly the issue of power capacity at the Premier Northern Lights (PNL) workings. Ascot has ordered a new transformer to enable simultaneous operation of multiple pieces of equipment, a critical step toward efficient production. Additionally, the company plans to double the camp space at the Premier site to accommodate more personnel as it gears up for the restart.

The Premier mill is expected to resume operations at an initial rate of 1,250 tonnes per day (tpd), with feedstock sourced from both PNL and the Big Missouri deposit. This will be achieved by running the 2,500-tpd mill on a two-week-on, two-week-off schedule. Ascot anticipates ramping up to full capacity of 2,500 tpd seven days a week by the first half of 2026, once the Silver Coin deposit is developed.

Exploration and Market Response

In parallel with the restart preparations, Ascot will launch an exploration drilling program in June to evaluate prospective sites near the Premier mill and other high-elevation targets. However, despite the positive funding news, Ascot’s shares dropped 5.3% by mid-morning on the day of the announcement, resulting in a market capitalization of C$128 million ($92m).

Historical Context and Challenges

The Premier gold project, located 25 km from Stewart, BC, was once North America’s largest gold mine, producing 2 million ounces between 1918 and 1952 across four deposits. Acquired by Ascot from Boliden in 2018, the mine briefly returned to production last April but was halted after five months due to insufficient underground development. The company initially aimed for a Q2 2025 restart but had to adjust its timeline.

Editorial Analysis

While the secured funding and August restart target are promising, questions remain about the sustainability of Ascot’s operational strategy. The two-week-on, two-week-off milling schedule may help manage costs initially, but it could limit output and delay full capacity utilization. Furthermore, the 5.3% drop in share price suggests investor skepticism about the project’s near-term profitability or the feasibility of meeting the revised timeline. Ascot must demonstrate progress in underground development and power upgrades to rebuild market confidence.

Conclusion:

Ascot Resources’ C$61.1 million financing marks a significant step toward reviving the historic Premier gold project. However, operational challenges and market reactions highlight the need for careful execution and transparency to ensure a successful restart by August and beyond.

Ascot Resources 获得新资金,目标8月重启Premier金矿项目

摘要: Ascot Resources 筹集6110万加元用于重启位于不列颠哥伦比亚省的Premier金矿项目,计划于8月初恢复生产。

引言

总部位于温哥华的矿业公司Ascot Resources(TSX: AOT)宣布,计划于8月初重启位于不列颠哥伦比亚省西北部的Premier金矿项目。此前,公司成功完成了一轮6110万加元(约合4400万美元)的融资,将用于资助该历史悠久的矿场关键升级和运营改进。

资金与运营升级

新获得的资金将解决关键的运营瓶颈问题,特别是Premier Northern Lights (PNL) 矿区的电力容量不足问题。Ascot已订购一台新的变压器,以支持多台设备同时运行,这是实现高效生产的关键一步。此外,公司计划将Premier矿场的营地空间扩大一倍,以容纳更多人员,为重启做好准备。

Premier选矿厂预计将以初始速率1250吨/天(tpd)恢复运营,原料来自PNL和Big Missouri矿床。这将通过以两周开、两周关的模式运行2500吨/天的选矿厂来实现。Ascot预计,到2026年上半年,一旦Silver Coin矿床开发完成,选矿厂将以设计产能2500吨/天、每周七天的速度全面运营。

勘探与市场反应

在重启准备的同时,Ascot将于6月启动一项勘探钻探计划,评估Premier选矿厂附近的潜在地点以及其他高海拔目标。然而,尽管融资消息利好,Ascot股价在公告发布当日上午下跌5.3%,公司市值降至1.28亿加元(约合9200万美元)。

历史背景与挑战

Premier金矿项目位于不列颠哥伦比亚省斯图尔特镇以北25公里处,曾是北美最大的金矿,在1918年至1952年间从四个矿床共生产了200万盎司黄金。Ascot于2018年从瑞典Boliden公司收购该矿,并于去年4月短暂恢复生产,但仅五个月后因地下开发不足而暂停。公司最初计划于2025年第二季度重启,但不得不调整时间表。

编辑分析

虽然获得6110万加元的融资以及8月重启目标令人振奋,但Ascot的运营策略可持续性仍存在疑问。两周开、两周关的选矿计划可能有助于初期控制成本,但可能会限制产量并延迟全面产能的实现。此外,股价下跌5.3%表明投资者对项目短期盈利能力或修订时间表的可行性持怀疑态度。Ascot必须在地下开发和电力升级方面展示进展,以重建市场信心。

结论:

Ascot Resources 的6110万加元融资标志着重振历史悠久的Premier金矿项目的重要一步。然而,运营挑战和市场反应凸显了谨慎执行和透明度的重要性,以确保8月及未来的成功重启。