Greatland Gold lays out two-year plan for Telfer to bridge output gap

Published: 2025-04-16 16:53 Author: Jackson Chen
Source: MINING.COM (Original Article)

AI Analysis & Insights

Greatland Gold Unveils Two-Year Production Plan for Telfer Mine to Bridge Output Gap

Summary: Greatland Gold targets 280,000-320,000 oz. of annual gold production at Telfer mine over the next two years, bridging the gap until Havieron mine starts in 2028, while refining plans and exploring resource upgrades.

Introduction

Greatland Gold (AIM: GGP), an Australian mining company, has outlined an ambitious two-year production plan for its recently acquired Telfer mine, purchased from Newmont last fall. The company aims to achieve an annual output of 280,000 to 320,000 ounces of gold through fiscal year 2027, addressing a previously identified production gap before the Havieron mine begins operations.

Telfer Mine Production Strategy

The production target is based on existing inventory from the West Dome open pit and Main Dome underground operations, supplemented by run-of-mine and low-grade stockpiles. Greatland is confident in extending Telfer’s operational timeline, with managing director Shaun Day noting an 18-month extension of dual train processing after just five months of ownership. The company also reported 90,000 oz. of gold production in the March 2025 quarter, signaling steady progress.

Currently, 20% of Telfer’s inventory consists of inferred resources and unclassified mineralization. However, Greatland is optimistic about converting these into higher-confidence measured and indicated categories, leveraging Telfer’s 40-year operational history and extensive drilling data. Ongoing drilling aims to refine resource estimates and potentially expand open pit and underground deposits beyond FY2027.

Havieron Integration and Future Growth

Looking ahead, the Havieron project, also acquired from Newmont, is slated to start production in FY2028. Greatland anticipates this integration will significantly reduce costs and boost production volumes. Havieron holds estimated reserves of 25 million tonnes at 3 grams per tonne of gold, supporting an annual output of 221,000 oz. over its first 15 years at a throughput rate of 2.8 million tonnes per annum. The company is exploring an expansion to 4-4.5 million tonnes, with a feasibility study expected to conclude in the second half of 2025.

Analysis and Perspective

While Greatland’s plan appears robust, relying on inferred resources introduces uncertainty. The conversion to higher-confidence categories is not guaranteed and depends on drilling outcomes and market conditions. Additionally, the ambitious Havieron expansion hinges on the feasibility study, which could reveal operational or financial challenges. However, Telfer’s long history and Greatland’s proactive approach to resource evaluation provide a solid foundation for optimism. Investors should monitor drilling results and Havieron’s development closely, as these will be critical to sustaining momentum.

Conclusion:

Greatland Gold’s two-year plan for Telfer mine offers a strategic bridge to maintain production levels until Havieron comes online. While the targets are promising, the reliance on resource conversion and future expansions warrants cautious optimism. Continued transparency and successful execution will be key to realizing this vision.

Greatland Gold公布Telfer矿两年生产计划以弥补产量缺口

摘要: Greatland Gold计划在未来两年内通过Telfer矿实现每年28万至32万盎司的黄金产量,填补Havieron矿2028年投产前的缺口,同时完善计划并探索资源升级。

引言

澳大利亚矿业公司Greatland Gold (AIM: GGP) 为其最近从Newmont手中收购的Telfer矿制定了为期两年的雄心勃勃的生产计划。公司目标是在2027财年之前实现每年28万至32万盎司的黄金产量,以解决Havieron矿投产前的产量缺口问题。

Telfer矿生产策略

该生产目标基于现有库存,包括目前活跃的West Dome露天矿和Main Dome地下矿的资源,以及矿山开采和低品位库存。Greatland对延长Telfer的运营时间充满信心,董事总经理Shaun Day表示,在收购仅五个月后,已将双线加工时间延长了18个月。公司还报告称,2025年3月季度Telfer矿生产了9万盎司黄金,显示出稳定的进展。

目前,Telfer矿20%的库存为推断资源和未分类矿化物。然而,Greatland乐观地认为,凭借Telfer长达40年的运营历史和大量钻探数据,这些资源有望转化为更高置信度的测定和指示类别。持续的钻探工作旨在优化资源估算,并可能在2027财年后进一步扩展露天和地下矿藏。

Havieron整合与未来增长

展望未来,同样从Newmont收购的Havieron项目预计将于2028财年开始投产。Greatland预计,这一整合将显著降低成本并提升产量。Havieron矿藏目前估计储量为2500万吨,黄金品位为每吨3克,预计在最初15年内每年生产22.1万盎司黄金,基于每年280万吨的稳定开采吞吐量。公司正在探索将吞吐量扩大至400万至450万吨,可行性研究预计将于2025年下半年完成。

分析与观点

尽管Greatland的计划看似稳健,但依赖推断资源带来了不确定性。资源向更高置信度类别的转化并非必然,取决于钻探结果和市场条件。此外,Havieron的雄心勃勃的扩建计划依赖于可行性研究,可能会揭示运营或财务挑战。然而,Telfer的悠久历史和Greatland对资源评估的积极态度为其乐观前景提供了坚实基础。投资者应密切关注钻探结果和Havieron的开发进展,因为这些将是维持发展势头的关键。

结论:

Greatland Gold为Telfer矿制定的两年计划提供了一个战略性桥梁,以维持产量水平直至Havieron投产。尽管目标令人振奋,但对资源转化和未来扩建的依赖需要谨慎乐观。持续的透明度和成功执行将是实现这一愿景的关键。